Post-Bay County Construction Co.
- A-1. Construction of 350′ of track for storage of coaches and crippled cars. Work begun 10-15-1922; Project completed and turned over to operation 11-15-1922.
- A-2. Construction of re-inforced concrete box culvert 9′ x 12′ x 60′ under PH&DRR main line and Rapid Railway at Bunce Creek. Rapid Railway to pay $800 as their proportion of the cost. Work done by C. R. Cummins company. Work begun 11-15-1922; Project completed 12-15-1922. Total cost of project: $4809.30 minus $800 from Rapid Railway, $4,009.30
- A-3.
- A-4.
- A-5. Purchase of 2-four wheels caboose cars, steel center sills from General Equipment Company. No. 1 & 2. Date of Change: 1-15-1923. Amount: $1,494.86.
- A-6. Finishing upstairs offices and installing plumbing and lighting fixtures in yard offices at Port Huron. Work begun 2-1-1923; Project completed 8-31-1923.
- A-7.
- A-8. Installation of one 26″ back gear crank shaper and one hack saw in shop at Port Huron. Work begun 6-15-1923. Project completed 7-15-1923.
- A-9. Construction of cement floor in shop and two stalls of Round-house, 4000 sq. ft. cement. Work begun 6-1-1923; Project completed 6-30-1923.
- A-10. Installation of Hot water heating system in Agents & Account Dept. Offices at Port Huron. Work begun 7-15-1923; Project completed 8-15-1923.
1 Ideal Arcola #5 P.A. 450 heating outfit complete
with 2-80 ft. and 4-75 ft. Radia. - A-11. Construction of galvanized iron partition in Roundhouse separating shop from engine house. Work begun 7-15-1923; Project completed 8-15-1923.
2 M sq. ft. galv. sheathing. - A-12.
- A-13.
- A-14. Construction of 28′ addition to North end of Pine River Bridge and laying guard rail on entire bridge. Work begun 9-15-1923; Project completed 10-15-1923.
- A-15. Relaying 6216′ main line track between Sta. 76+06 and Sta. 146+00 with 80# rail. Work begun 11-15-1923; Project completed 12-15-1923.
- To be continued…